9 March 2026 F&I Group

Neville Hall

Contractor: Brims Construction
Project Location: Newcastle City Centre

Project Overview

Neville Hall, originally built in the 1870s as a country house, is a Grade II listed building located in Newcastle City Centre. The project required specialist scaffolding solutions to support refurbishment works while protecting the historic structure.

Ingleford Scaffolding Ltd worked with Brims Construction to design and install a range of bespoke scaffold systems across the building.

The Solution

Multiple scaffold structures were designed to provide safe access across the site. One key installation included an access lifting beam trolley system around the core of the building, allowing materials to be moved safely to the roof areas.

A NIKO rail system was also incorporated to allow glazing panels to be transported securely around the scaffold. Due to access restrictions from a neighbouring building overhang, the scaffold design was adapted and re erected to step under and around the obstruction in less than 48 hours.

The Result

The bespoke scaffold solutions enabled safe and efficient access for the refurbishment works while accommodating the constraints of the listed building and surrounding structures throughout the 52 week project.

Delivering excellence
in every project

Explore projects from across the F&I Group, showcasing the quality, expertise and dedication behind every job, each one reflecting our commitment to excellence and precision.

Looking for a career that reaches new heights?

Join a team that values skill, safety, and ambition. At John Flowers, we offer exciting opportunities to grow your career across a range of specialist trades, with hands-on training, ongoing support, and professional development every step of the way.

Work with us Work with us

Want to learn more?
Download our brochure

Receive our latest company brochure and sign up for occasional updates, project highlights, and industry insights from F&I Group.